Field Relationships
32
Project Work
Project Estimated Hours
Project Level User Defined Fields (Proj/Task Category)
Project Cost
Project Estimated Cost
Project Level User Defined Fields (Proj/Task Category)
Project Actual Hours
Project Level User Defined Fields (Proj/Task Category)
Task WBS Code
Task Description
Task Code
Task Level User Defined Fields (Proj/Task Category)
Task Duration
Task Estimated Hours
Task Level User Defined Fields (Proj/Task Category)
Task Work
Task Estimated Hours
Task Level User Defined Fields (Proj/Task Category)
Task Cost
Task Estimated Cost
Task Level User Defined Fields (Proj/Task Category)
Task Priority
Task Level User Defined Fields (Proj/Task Category)
Task Unique ID
Task Code
Task Level User Defined Fields (Proj/Task Category)
% Complete
Project Level User Defined Fields (Proj/Task Category)
Task Level User Defined Fields (Proj/Task Category)
Microsoft Project File
Name
Project Description
Project Level User Defined Fields (Proj/Task Category)
If you map the Microsoft
Project file name to a User De-
fined Field, only the specified
User Defined Field for the
project (not the task) will be up-
dated.
Custom Fields (Task
Type)
Task Description
Task Code
Task Estimated Cost
Task Estimated Hours
Task Level User Defined Fields (Proj/Task Category)
When you map from Microsoft
Project custom fields to Web
TimeSheet User Defined
Fields, calculated fields are ex-
cluded.
Custom Fields (Re-
source Type)
User Defined Fields (User Category)
When you map from Microsoft
Project custom fields to Web
TimeSheet User Defined
Fields, calculated fields are ex-
cluded.
Microsoft Project Field
(source)
Web TimeSheet Field
(target)
Notes